Tshipi e Ntle Manganese Mining currently holds a prospecting right for manganese on portion 2 of the Farm Wessels 227 and the remaining extent and portions 3 and 4 of the Farm Dibaghomo 226, north of Black Rock in the Northern Cape Province. Tshipi is planning to apply to the DMR for a mining right over
The Okiep Copper Project (OCP) is located in the Northern Cape, approximately 570km north of Cape Town and 450km west of the flagship Prieska Copper Zinc Project. Orion has acquired the surface ownership rights of properties known as Farm Nababeep and Farm Plaatjesfontein (Farms Nababeep) which overlie
Upgrades, additions and routine road maintenance of National Route 10 Sections 5 to 8 between Kopieskraal from km 31.322 and Omdraai Vlei at km 61.641 in the Pixley Ka Seme District Municipality, Northern Cape. The project value is R 107 661 724.40. The exact GPS location is not known and the marker
The proposed Sishen Expansion Project at SIOM comprises of further pit expansions that include Far south pushback 21 and 19, Lylyveld pit expansion, C&G stockpile at Far south and Lylyveld pit, Moolmans workshop, access road and pollution control dam, proposed Far south Waste Rock Dump,heavy and light
Construction and operation of grid connection infrastructure consisting of a single circuit 132kV power line between the existing Emil Traction Substation and the authorised Olifantshoek Substation located near the town of Olifantshoek located within the Gamagara Local Municipality and the greater John
Construction of grid connection infrastructure for the Zonnequa wind farm in the Northern Cape. The scope of works will include the construction of a collector substation, a double - circuit 132kV power line and infrastructure including access roads and laydown areas. This development traverses the following
Construction of the Khunab Solar Grid Connection on Portion 3 of the Farm McTaggarts Camp 453; Portion 12 of the Farm Klip Punt 452 and Olyvenhouts Drift Settlement Agricultural Holding 1080 in the Northern Cape. The grid connection solution will include specific grid connection infrastructure to cater
Construction of the Teraco Facilities in Isando and Bredell, Kempton Park, Gauteng. The development includes building the Isando Campus JB1/JB3/JB5 (70MW), Bredell Campus JB2/JB4 (64MW), Cape Town Campus CT1/CT2 (50MW), and Durban (1MW).
Construction of the new Vantage Data Centre 3, in Isando, Kempton Park, Gauteng. The new data centre is located 2km from the Teraco site in Isando and it will feature dedicated offices, general work spaces, break areas, conference rooms, meeting spaces and secure storage areas amongst other amenities.
Construction of the proposed new JB3 addition to the Teraco Isando Data Centre Campus situated in Kiln Street, Erf 302 - Erf 305, Isando, Extension 1, Kempton Park, Gauteng. This hyper scale data centre will stand as the largest entity of its kind in Africa at 60 MVA capacity.
The first of two
Construction of the 2 level Teraco Data Centre situated in Bredell, Kempton Park, Gauteng. It will comprise 60 000m² of building structure serviced by 80MW of utility power supply servicing 50MW of critical power load. The GPS is : 26°01'29.5"S 28°16'01.8"E.
Construction of the Vantage Data Centre 2 in Isando, Kempton Park, Gauteng. The new data centre is located 2km from the Teraco site in Isando and it will feature dedicated offices, general work spaces, break areas, conference rooms, meeting spaces and secure storage areas amongst other amenities. The
Construction of a new hyperscale Teraco Data Centre, that will be known as JB5, situated at Isando, Kempton Park, Johannesburg, Gauteng. Key Facts, JB5 comprises 55 000 sqm of building structure serviced by 120MVA of utility power supply. JB5 will be build in a single phase and includes 12 1000sqm halls.
Construction of a new 30MW data centre facility in Cape Town, Western Cape. The CT2 comprises 25,000 square meters of building structure, 8,000sqm of data hall space, and 18 megawatts of critical power load.. GPS coordinates lat: -33.9015065; long: 18.6791515.
Construction of the proposed new 2 level Teraco Data Centre situated in Bredell, Kempton Park, Gauteng. Phase one of the JB4 data centre is scheduled to be completed in the first quarter of 2022. The JB4 data centre will comprise a 50 000m² of building structure serviced by 80MW of utility power supply,
Construction of Teraco CT2 Data Centre Phase 2 on Rubicon Boulevard, Brackenfell South in Cape Town, Western Cape. The GPS location is 33°54'21.2"S 18°40'49.3"E
Construction of a wind energy facility and associated infrastructure, Kokerboom 1 wind farm in the Northern Cape. Kokerboom 1 wind farm is located on farm portions Leeuwberg Rivier (RE/1163) and Kleine Rooiberg (RE/227) approximately 50km North of Loeriesfontein, 85km West of Brandvlei and 160km southeast
Lehating Mining proposes to establish a new manganese mining operation near Hotazel in the Northern Cape. The project will involve underground mining accessed via a decline shaft, crushing, screening and transport of manganese ore as well as associated infrastructure and services. The mining and related