REFURBISHMENT OF THE HEROLD’S BAY WASTEWATER TREATMENT WORKS

Refurbishment of the Herold’s Bay Wastewater Treatment Works


01-10-2024
Read : 6 times
George Herald
Source

The refurbishment of the Herold’s Bay Wastewater Treatment Works will have an impact on residents and road users during the construction period from
September 2024 to July 2025. The estimated construction duration is 10 months.



PROJECT:



REFURBISHMENT OF THE HEROLD’S BAY WASTEWATER TREATMENT WORKS



DESCRIPTION:



Refurbishment of existing Wastewater Stabilization Ponds. The existing concrete lining will be demolished and removed from the site. A new underdrain system will be installed, and the existing cement lining will be replaced with a waterproof lining system. A new tanker discharge chamber will be constructed with the required access road.



PROJECT PERIOD:



September 2024 to July 2025



SERVICE DISRUPTION:



Municipal services may be disrupted during construction. Advance notification of planned temporary disruptions will be sent out via social media.



WORKING HOURS:



Working hours will be from 07h00 to 17h00 on Mondays to Fridays and 07h00 – 14h00 on Saturdays as may be needed from time to time.



TRAFFIC IMPACT:



Caution needs to be exercised by residents, road users and pedestrians throughout the duration of the construction period.



ACCESS TO SITE:



Access to the site will be strictly controlled. Any member of the public who enters the site will have to comply with the relevant requirements in terms of the Health and Safety Act.



PROJECT ENQUIRIES Mr Francois Harris – 072 580 2729



The George Municipality apologises for any inconvenience and appeals to the public to be patient and exercise caution throughout the construction period. Please look out for all temporary road signage and construction personnel.